The "Nuclear Power 2010 Program" was launched in 2002 by President George W. Bush in order to restart orders for nuclear power reactors in the U.S. by providing subsidies for a handful of Generation III+ demonstration plants. The expectation was that these plants would come online by 2010, but this expectation was not met. ==Overview== The "Nuclear Power 2010 Program" was unveiled by the U.S. Secretary of Energy Spencer Abraham on February 14, 2002 as one means towards addressing the expected need for new power plants. The program is a joint government/industry cost-shared effort to identify sites for new nuclear power plants, to develop and bring to market advanced nuclear plant technologies, evaluate the business case for building new nuclear power plants, and demonstrate untested regulatory processes leading to an industry decision in the next few years to seek Nuclear Regulatory Commission (NRC) approval to build and operate at least one new advanced nuclear power plant in the United States. Three consortia responded in 2004 to the U.S. Department of Energy's solicitation under the Nuclear Power 2010 initiative and were awarded matching funds. *The Dominion-led consortium includes General Electric (GE) Energy, Hitachi America, and Bechtel Corporation, and has selected General Electric's Economic Simplified Boiling Water Reactor (ESBWR, a passively safe version of the BWR). *The NuStart Energy Development, LLC consortium consists of DTE Energy, Duke Energy, EDF International North America, Entergy Nuclear, Exelon Generation, Florida Power & Light Co., Progress Energy, SCANA Corporation, Southern Company, GE Energy, Tennessee Valley Authority (TVA), and Westinghouse Electric Company and has chosen the General Electric Economic Simplified Boiling Water Reactor (ESBWR) and the Westinghouse Advanced Passive 1000 (AP1000, a PWR) reactor as candidates. The NuStart consortium was disbanded on 30 June 2012. *The third consortium, led by TVA, includes General Electric, Toshiba, USEC Inc., Global Fuel-Americas, and Bechtel Power Corp., and will develop a feasibility study for a TVA site based on the General Electric Advanced Boiling Water Reactor (ABWR). On September 22, 2005, NuStart selected Port Gibson (the Grand Gulf site) and Scottsboro (the Bellefonte site) for new nuclear units. Port Gibson will host an ESBWR (a passively safe version of the BWR) and Scottsboro an AP1000 (a passively safe version of the PWR). Entergy announced it will prepare its own proposal for the River Bend Station in St. Francisville. Also, Constellation Energy of Baltimore had withdrawn its Lusby and Oswego sites from the NuStart finalist list after on September 15 announcing a new joint venture, UniStar Nuclear, with Areva to offer EPR (European Pressurized Reactors) in the U.S.A.〔http://uk.biz.yahoo.com/050915/323/fs67q.html 〕 Finally, in October, 2005, Progress Energy announced it was considering constructing a new nuclear plant and had begun evaluating potential sites in central Florida. South Carolina Electric & Gas announced on February 10, 2006 that it chose Westinghouse for a plant to be built at the V.C. Summer plant in Jenkinsville, South Carolina. NRG Energy announced in June, 2006 that it would explore building two ABWRs at the South Texas Project. (Four ABWRs are already operating in Japan.) The original goal of bringing two new reactors online by 2010 was missed, and "of more than two dozen projects that were considered, only two showed signs of progress and even this progress was uncertain". As of June 2015, the Vogtle and VC Summer plants (a total of four reactors) are under construction, with expected completion around 2020. 抄文引用元・出典: フリー百科事典『 ウィキペディア(Wikipedia)』 ■ウィキペディアで「Nuclear Power 2010 Program」の詳細全文を読む スポンサード リンク
|