翻訳と辞書
Words near each other
・ Putnam family
・ Putnam Farm
・ Putnam Formation
・ Putnam Griswold
・ Putnam Grounds
・ Putnam Hall School
・ Putnam Hall, Florida
・ Putnam High School
・ Putnam Hill Formation
・ Putnam Hill Historic District
・ Putnam House
・ Putnam Investments
・ Putnam Lake, New York
・ Putnam Magazine
・ Putnam Memorial State Park
Putnam model
・ Putnam Museum
・ Putnam Park
・ Putnam Park (disambiguation)
・ Putnam Railroad Station
・ Putnam Street Bridge
・ Putnam Street Historic District
・ Putnam Town Hall
・ Putnam Township
・ Putnam Township, Anderson County, Kansas
・ Putnam Township, Fayette County, Iowa
・ Putnam Township, Linn County, Iowa
・ Putnam Township, Michigan
・ Putnam Township, Tioga County, Pennsylvania
・ Putnam Transit


Dictionary Lists
翻訳と辞書 辞書検索 [ 開発暫定版 ]
スポンサード リンク

Putnam model : ウィキペディア英語版
Putnam model
The Putnam model is an empirical software effort estimation model.
The original paper by Lawrence H. Putnam published in 1978 is seen as pioneering work in the field of software process modelling.

As a group, empirical models work by collecting software project data (for example, effort and size)
and fitting a curve to the data. Future effort estimates are made by providing size and calculating the associated effort using the equation which fit the original data (usually with some error).
Created by Lawrence Putnam, Sr. the Putnam model
describes the ''time'' and ''effort'' required to finish a software project of specified ''size''.
SLIM (Software LIfecycle Management) is the name given by Putnam to the proprietary suite of tools his
company QSM, Inc. has developed based on his model. It is one of the earliest
of these types of models developed, and is among the most widely used. Closely related software parametric models are
Constructive Cost Model (COCOMO),
Parametric Review of Information for Costing and Evaluation – Software (PRICE-S), and
Software Evaluation and Estimation of Resources – Software Estimating Model (SEER-SEM).
==The Software Equation==

While managing R&D projects for the Army and later at GE, Putnam noticed software staffing profiles followed
the well-known Rayleigh distribution.〔(【引用サイトリンク】 publisher = Computer Aid, Inc. )
Putnam used his observations about productivity levels to derive the software equation:
:\frac } = \textrm^ \cdot \textrm^
where:
* Size is the product size (whatever size estimate is used by your organization is appropriate). Putnam uses ESLOC (Effective Source Lines of Code) throughout his books.
* B is a scaling factor and is a function of the project size.〔(【引用サイトリンク】 Putnam Special Skills Factor Table )

* Productivity is the Process Productivity, the ability of a particular software organization to produce software of a given size at a particular defect rate.
* Effort is the total effort applied to the project in person-years.
* Time is the total schedule of the project in years.
In practical use, when making an estimate for a software task the software equation is solved for ''effort'':
:\textrm = \left(\frac \cdot \textrm^}\right )^3 \cdot B
An estimated software size at project completion and organizational process productivity is used. Plotting ''effort'' as a function of ''time'' yields the ''Time-Effort Curve''. The points along the curve represent the estimated total effort to complete the project at some ''time''. One of the distinguishing features of the Putnam model is that total effort decreases as the time to complete the project is extended. This is normally represented in other parametric models with a schedule relaxation parameter.
:Time-Effort Curve
This estimating method is fairly sensitive to uncertainty in both ''size'' and ''process productivity''.
Putnam advocates obtaining process productivity by calibration:〔
:\textrm = \frac } \right )^ \cdot \textrm^ }
Putnam makes a sharp distinction between 'conventional productivity' : ''size'' / ''effort''
and process productivity.
One of the key advantages to this model is the simplicity with which it is calibrated. Most software organizations, regardless of maturity level can easily collect ''size'', ''effort'' and duration (''time'') for past projects. Process Productivity, being exponential in nature is typically converted to a linear ''productivity index'' an organization can use to track their own changes in productivity and apply in future effort estimates.〔(【引用サイトリンク】 Putnam Productivity Parameter Table )